14ymedio, Madrid, 20 March 2024 — The main thermoelectric power plant in the country, the Antonio Guiteras of Matanzas, left the National Electric System (SEN) just 24 hours after its synchronization. Without further details, early in the morning of Wednesday, the Electric Union of Cuba (UNE) announced that its only unit is out of service “due to a breakdown.”
The Guiteras entered the SEN on Monday, March 18, after being out of service 17 days for maintenance. Its arrival was eagerly awaited, since it is the plant with the most generation, 280 megawatts (MW) at full capacity. Journalist José Miguel Solís, of Radio Rebelde in Matanzas, follows the wanderings of the thermoelectric plant. He published an image of the Guiteras in full operation shortly before 1:00 in the afternoon on Tuesday, when its capacity was 270 MW.
According to Radio 26 of Matanzas, in the early hours of Wednesday the plant suffered an “inconvenience in the boiler,” in addition to a steam leak in one of the turbines, which the technicians hope to solve in a short time. “The correction of the breakdowns, natural after an intense maintenance of 1,500 parts, will allow the reinstatement of the unit before the time of maximum de